First of all, we have the best and most first-class operating system, in addition, we also solemnly assure users that users can receive the information from the CDCS learning material within 5-10 minutes after their payment. Second, once we have written the latest version of the CDCS learning material, our products will send them the latest version of the CDCS Training Material free of charge for one year after the user buys the product. Last but not least, our perfect customer service staff will provide users with the highest quality and satisfaction in the hours.
Topic | Details |
---|---|
Topic 1 |
|
Topic 2 |
|
Topic 3 |
|
As the rapid development of the world economy and intense competition in the international, the leading status of knowledge-based economy is established progressively. A lot of people are in pursuit of a good job, a CDCS certification, and a higher standard of life. You just need little time to download and install it after you purchase, then you just need spend about 20~30 hours to learn it. We are glad that you are going to spare your precious time to have a look to our CDCS Exam Guide.
NEW QUESTION # 39
In which stage of the data center life cycle does commissioning take place?
Answer: B
Explanation:
Commissioning occurs during the Implementation stage of the data center life cycle. This phase involves the final testing and verification of systems and equipment to ensure they meet design specifications and operational requirements before the data center goes live.
Detailed Explanation:
The Implement phase includes activities such as installation, configuration, and testing. Commissioning is a crucial step that validates the performance and reliability of all critical systems, including power, cooling, and network infrastructure, to ensure they operate as intended under various conditions. Proper commissioning helps identify and resolve any issues before the data center becomes fully operational.
EPI Data Center Specialist References:
EPI training emphasizes that commissioning is essential for verifying that the data center meets design and performance criteria, aligning with best practices in data center project management to minimize risks and ensure readiness for operation.
NEW QUESTION # 40
It is assumed that EMF shielding material must be installed as the EMF levels coming from the transformer room into the computer room are measured at 100mG. The transformer room is approximately 10 meters away from the computer room and is separated by a corridor. You can assume that no physical issues are present for installing shielding material at any area/location.
Where should you recommend the shielding material to be installed?
Answer: B
Explanation:
EMF shielding is most effective when installed close to the source of the EMF, which in this case is the transformer room. Shielding at the source contains the magnetic fields before they spread, minimizing exposure throughout the facility, including the computer room.
Detailed Explanation:
Placing shielding close to the EMF source minimizes the area impacted by electromagnetic interference, as it reduces the distance over which the EMF can spread. Shielding materials near the source can absorb or redirect EMF, providing the most effective reduction of EMF levels in adjacent spaces, like the data center.
EPI Data Center Specialist References:
EPI data center training advises positioning shielding close to the EMF source to contain fields more effectively and reduce interference in critical areas. This method is more efficient and cost-effective, as it limits the spread of EMF from the point of origin.
NEW QUESTION # 41
The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.
What is the set-up in this data center?
Answer: B
Explanation:
A 2(N+1) configuration implies two independent UPS systems, each with N+1 redundancy. This configuration provides high availability by ensuring that each UPS system can independently support the load with an additional unit for redundancy. Given the 80 kW load, this setup implies that two separate N+1 systems are running, providing reliability and fault tolerance for the data center's power needs.
Detailed Explanation:
The N+1 notation denotes that each system has one additional unit beyond what is needed to carry the load, providing redundancy. With 2(N+1), there are two such setups, ensuring that if one fails, the other can still support the load without interruption, fulfilling high availability requirements.
EPI Data Center Specialist References:
EPI teaches that multiple redundant systems, such as 2(N+1), enhance data center reliability by ensuring that power is maintained even if a failure occurs in one system. This meets the stringent demands for uptime in critical environments.
NEW QUESTION # 42
A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.
Are new floor loading calculations required?
Answer: C
Explanation:
For heavy equipment, such as a network storage device weighing approximately 600 kg/1,300 lbs, new floor loading calculations are indeed required, particularly since the rack is non-standard. A structural engineer, approved by the building owner, should conduct these calculations to ensure the floor can safely support the new load without risking structural integrity.
Detailed Explanation:
Data centers are designed with specific floor load ratings, which are determined during the design phase based on anticipated equipment. When adding or replacing equipment that is significantly heavy or non-standard, reassessing the floor's capacity is essential to avoid overloading. A structural engineer has the expertise to verify if the existing floor can accommodate the weight and, if not, can recommend reinforcement measures.
This step ensures compliance with safety standards and helps prevent damage to the infrastructure, which could lead to costly repairs or even catastrophic failure in extreme cases.
EPI Data Center Specialist References:
EPI Data Center Specialist training advises that any changes in the data center load, particularly involving non-standard and heavy equipment, warrant a structural assessment. Ensuring compliance with floor load capacity is a critical safety and operational concern, as underscoring data center infrastructure reliability and safety is a priority in EPI's best practices.
NEW QUESTION # 43
Is it allowed to make design changes during the implementation phase?
Answer: D
Explanation:
Design changes during the implementation phase are generally allowed only when there is a strong business and/or technical justification. Changes at this stage can lead to delays, increased costs, or compromise design integrity. Thus, a rigorous assessment is required to ensure any modifications are essential and provide clear benefits or address critical issues.
Detailed Explanation:
Changes post-design freeze should be minimized to avoid scope creep and additional costs. However, if a technical issue arises that would affect operational goals, or a business need warrants modification, justified changes are permissible, following an impact assessment and approval process.
EPI Data Center Specialist References:
EPI project management guidelines recommend a controlled change management process during implementation, allowing changes only when they align with critical objectives or address unforeseen issues that affect the project's success.
NEW QUESTION # 44
......
In the past few years, EXIN certification CDCS exam has become an influenced computer skills certification exam. However, how to pass EXIN certification CDCS exam quickly and simply? Our 2Pass4sure can always help you solve this problem quickly. In 2Pass4sure we provide the CDCS Certification Exam training tools to help you pass the exam successfully. The CDCS certification exam training tools contains the latest studied materials of the exam supplied by IT experts.
Reliable CDCS Exam Questions: https://www.2pass4sure.com/EPI-Data-Centre/CDCS-actual-exam-braindumps.html
2025 Latest 2Pass4sure CDCS PDF Dumps and CDCS Exam Engine Free Share: https://drive.google.com/open?id=1mi-4oMkZD2poCw1Oyoe5vz17nw0OSPhY
Tags: Free CDCS Download, Reliable CDCS Exam Questions, CDCS Exam Registration, Test Certification CDCS Cost, Positive CDCS Feedback